The question

To ask the Scottish Government which elements of Dumfries and Galloway Council’s claim under the Bellwin Scheme to cover additional expenditure incurred by the snowstorms of March 2013 were deemed ineligible for assistance because they were not (a) incurred as a result of providing relief or carrying out works to safeguard life or property or prevent suffering or severe inconvenience, (b) of a revenue nature, (c) net of any receivable income from other sources, (d) of an uninsurable nature and (e) incurred within a two month period from the date of the incident and what the total financial value was of these elements.

The answer

Answered by John Swinney on 5 Sep 2013 · 7 days after it was lodged, on time

Dumfries and Galloway’s claim under the Bellwin scheme following the severe winter weather in late March 2013 was submitted in two parts. The second part of the claim amounted to over £794,000 for repairing the damage caused to the roads by the severe snow storms. This part of the claim was ruled out because the expenditure was to be incurred outwith the two month period following the incident. The council, in submitting the claim accepted that this part of the claim was outwith the two month period.
This left the first part of the claim which amounted to almost £965,000 of which around £650,000 was in respect of the immediate snow clearing and providing an emergency response following the incident. Unfortunately, this did not breach the council’s published Bellwin threshold of £679,994 that they are expected to budget for (0.2% of their net revenue budget) to cope with emergency situations. The remainder of the first part of the claim (almost £315,000) was in respect of work on drainage, fencing, dyking, hedging, resurfacing, surface dressing and verge repair, none of which would fall under the eligible costs of the scheme as it was not work to safeguard life or property in the immediate aftermath of an emergency situation.

In the Official Report

No contribution in the Official Report cites S4W-16910 by reference.