Written Question · S4W-16538 · Session 4

Further to the answer to question S4W-16190 by John Swinney on 26 July 2013, how much of the money allocated for 2012-13 each project spent.

Answered Asked by Gavin Brown Con Lodged 26 Jul 2013

The question

To ask the Scottish Government, further to the answer to question S4W-16190 by John Swinney on 26 July 2013, how much of the money allocated for 2012-13 each project spent.

The answer

Answered by John Swinney on 18 Sep 2013 · 54 days after it was lodged, 23 days after it was due

The provisional outturn figures for each project to 31 March 2013 is provided in the following table.
The main change from forecast spend was for renewable energy projects, as discussed with the Finance Committee at the 2012-13 Spring Budget Revision on 13 March 2013 and confirmed in subsequent correspondence on 3 April 2013. Much of the funding allocated for the Renewable Energy Investment Fund for 2012-13 could not be committed within that year, due to a lack of projects at the right stage for investment, and will be made available in future years instead.
Project
Projected Outturn £million
Section A: Low Carbon Investment/Renewables

Transport Scotland: Green Bus Fund
1.8
Regeneration: Rutherglen Low Carbon Zone (RCLZ)
0.8
Highlands and Islands Enterprise: Arnish Plant and Estate Improvements
1.1
Renewable Projects
1.5
TOTAL for section A
5.2

Section B: Housing and Regeneration

Housing: Priority investments within Local Authority Strategic Housing Investment Plans
- bring forward 300 homes
15
Housing year 2012-13 only: Priority investments within Local Authority Strategic Housing Investment Plans
- further 350 homes in addition to those from accelerating budget above
20
Govanhill
- Empty Homes Purchase
0.5
Govanhill
- Backcourt Improvements
0
Accelarated programme of developments in Riverside Inverclyde Urban Regeneration Company
2.4
Regeneration: High-growth pre-let office, Bridgeton 1,800 square meters.
0.5
TOTAL for section B
38.4

Section C: Infrastructure and Investment

Health: Maintenance to ensure assets are safe, effective and patient centred
- accelerated spend
15
Highlands and Islands Enterprise: Inverness Campus
6
Scottish Funding Council: West Highland College, Fort William – infrastructure expansion
0.2
Transport Scotland: Kennacraig, Kintyre, Phase 2 – causeway1
1.3
Transport Scotland: A75 Hardgrove to Kinmount
0.9
TOTAL for section C
23.4

Section D: Enterprise

Highlands and Islands Enterprise: Forres Enterprise Park – Extension of Roads
1.4
Highlands and Islands Enterprise: Forres Enterprise Park – Provide 2 Units
0.6
Highlands and Islands Enterprise: Building Development within Forres Enterprise zone
2.7
TOTAL for section D
4.7

Section E: Investment in Tourism – our Year of Natural Scotland

Forestry Commission Scotland
- upgrade of visitor facilities at David Marshall Lodge, Aberfoyle
4.3
Rural: National Parks
- visitor facility improvements within the National Parks
1.8
Royal Botanic Garden, Edinburgh
- commence replacement of the Garden's ageing glasshouses
1.5
Forestry Commission Scotland
- upgrade of visitor facilities at Queen's View Perthshire2
0.3
TOTAL for section E
4.3

F: Protecting our Cultural Assets/Investing in Tourism
Historic Scotland – Lews Castle development3
1.4
Historic Scotland
- essential maintenance of heritage assets
0.6
National Records of Scotland
- Thomas Thomson House
- urgent roof repairs
0.9
National Library of Scotland – internal and external fabric maintenance of city centre estate (George IV Bridge and Baden Powell House)4
0.2
National Galleries of Scotland – Energy saving maintenance project at the National Gallery5
0.5
Creative Scotland capital grants programme for local and regional cultural projects across Scotland
1
TOTAL for section F
4.6
Total for all sections
80.6