Further to the answer to question S4W-14385 by Keith Brown on 8 May 2013, whether the breakdown of the MV Hamnavoe will lead to an increase…
The question
To ask the Scottish Government, further to the answer to question S4W-14385 by Keith Brown on 8 May 2013, whether the breakdown of the MV Hamnavoe will lead to an increase in the cost of the 2012-18 Northern Isles contract and, if so, how much.
The answer
The full extent of the costs of the Northern Isles ferry services contract in the current contract year will only be finalised when the end year reconciliation takes place later this summer.
The detailed compensation mechanism in the Northern Isles contract does allow for certain costs to be shared between Serco NorthLink and the Scottish Government. However, other compensating factors will also come into play including the performance deductions from Serco NorthLink’s subsidy payments arising from the loss of the Hamnavoe.
The detailed compensation mechanism in the Northern Isles contract does allow for certain costs to be shared between Serco NorthLink and the Scottish Government. However, other compensating factors will also come into play including the performance deductions from Serco NorthLink’s subsidy payments arising from the loss of the Hamnavoe.