Written Question · S4W-15723 · Session 4

Further to the answer to question S4W-14388 by Keith Brown on 8 May 2013, what the revised annual subsidy is for the remainder of the 2012-…

Answered Asked by Richard Baker Lab Lodged 14 Jun 2013

The question

To ask the Scottish Government, further to the answer to question S4W-14388 by Keith Brown on 8 May 2013, what the revised annual subsidy is for the remainder of the 2012-18 contract, broken down by (a) vessel leasing, (b) chartering and (c) maintenance costs.

The answer

Answered by Keith Brown on 28 Jun 2013 · 14 days after it was lodged, on time

While the overall cost of the Northern Isles ferry services contract has already been announced, the Scottish Government does not provide a further breakdown of the various elements of our ferry service contract costs.
In addition, the costs of leasing and chartering vessels are covered by confidentiality agreements between their owners and the ferry operators.