Written Question · S4W-15570 · Session 4
Further to the answer to question S4W-08649 by Nicola Sturgeon 23 July 2012, when it estimates each of the health centres will be (a) compl…
The question
To ask the Scottish Government, further to the answer to question S4W-08649 by Nicola Sturgeon 23 July 2012, when it estimates each of the health centres will be (a) completed and (b) open to the public.
The answer
Outline business case approval was given for each of the health centres in May, and it is currently anticipated that they will be completed and open in summer 2015.
In the Official Report
No contribution in the Official Report cites S4W-15570 by reference.