Parliament Workbench
Data: Motions & questions to 3 Dec 2026

Written Question · S4W-15016 · Session 4

Further to the answer to question S4W-13913 by Derek Mackay on 18 April 2013, what changes have been made to (a) the issuing of planning an…

Answered Asked by Mary Scanlon Con Lodged 15 May 2013

The question

To ask the Scottish Government, further to the answer to question S4W-13913 by Derek Mackay on 18 April 2013, what changes have been made to (a) the issuing of planning and energy consents and (b) monitoring and enforcement to ensure that the freshwater pearl mussel is protected from the environmental impacts of development.

The answer

Answered by Derek Mackay on 28 May 2013 · 13 days after it was lodged, on time

Scottish Government online renewables planning advice on hydro schemes (last updated in July 2012) states that:
“Planning authorities should generally encourage developers to appoint Ecological Clerks of Works to ensure that agreed designs and construction techniques are followed following planning approval.”
No other specific changes have been made to (a) planning and energy consents, or (b) monitoring or enforcement.
It is routine practice where a hydro scheme requires an environmental impact assessment, that the Environmental Statement (ES) should state whether or not appropriately qualified environmental scientists or ecologists are to be used as Clerks of Works or in other roles during construction to provide specialist advice. Details of emergency procedures to be provided could be identified in the ES.

In the Official Report

No contribution in the Official Report cites S4W-15016 by reference.