Whether there has been an increase from nine to eleven trains per day on long distance services on the Highland main line, as indicated in …

Answered Asked by Murdo Fraser Con Lodged 19 Apr 2013

The question

To ask the Scottish Government whether there has been an increase from nine to eleven trains per day on long distance services on the Highland main line, as indicated in the SNP 2011 manifesto.

The answer

Answered by Keith Brown on 25 Apr 2013 · 6 days after it was lodged, on time

The first phase of the Highland Main Line improvements has been completed, introducing two additional services each way, to increase the number of trains per day from nine to eleven from December 2011 and providing journey time improvements of up to 18 minutes from December 2012.

In the Official Report

No contribution in the Official Report cites S4W-14360 by reference.