For what reason the Chief Executive of NHS Scotland asked Audit Scotland to add “helpful” points to the report, Management of patients on N…
The question
To ask the Scottish Government for what reason the Chief Executive of NHS Scotland asked Audit Scotland to add “helpful” points to the report, Management of patients on NHS waiting lists, as reported in the Sunday Herald on 31 March 2013.
The answer
There is an agreed protocol between Audit Scotland and the Scottish Government covering the arrangements for carrying out and clearing performance audit reports undertaken on behalf of the Auditor General for Scotland (AGS) which are published as part of the Scottish Public Finance Manual. The purpose of the protocol is to ensure that all relevant parties in the Scottish Government and Audit Scotland are aware of the arrangements for carrying out performance audits undertaken on behalf of the AGS and clearing draft reports.
The protocol states that in relation to the draft report/key messages:
“The project manager sends a copy of the key messages document and draft report to all project advisory group members, including the SG representative, for comment.”
For formal clearance of the report, the protocol says:
“The AGS sends a formal letter and a copy of the report to the relevant Accountable Officer. The AGS’s letter specifies the date when comments are due back (this is three weeks from the date of the letter) and asks for confirmation of the factual accuracy of the report and any other comments on the presentation and conclusions.”
While the Scottish Government can provide comment on the draft report, the final decision on what to include in the report is solely the responsibility of Audit Scotland. The comments provided were in line with standard procedures where Audit Scotland asked for comments on the draft report. In the interest of accuracy, Audit Scotland accepted a number of points raised and amended the final report accordingly, in exactly the same way as has been done on many other occasions.
The protocol states that in relation to the draft report/key messages:
“The project manager sends a copy of the key messages document and draft report to all project advisory group members, including the SG representative, for comment.”
For formal clearance of the report, the protocol says:
“The AGS sends a formal letter and a copy of the report to the relevant Accountable Officer. The AGS’s letter specifies the date when comments are due back (this is three weeks from the date of the letter) and asks for confirmation of the factual accuracy of the report and any other comments on the presentation and conclusions.”
While the Scottish Government can provide comment on the draft report, the final decision on what to include in the report is solely the responsibility of Audit Scotland. The comments provided were in line with standard procedures where Audit Scotland asked for comments on the draft report. In the interest of accuracy, Audit Scotland accepted a number of points raised and amended the final report accordingly, in exactly the same way as has been done on many other occasions.