Further to the answer to question S4W-13003 by Fergus Ewing on 5 March 2013, whether it will provide an estimate of the jobs delivered by e…

Answered Asked by Liam McArthur LD Lodged 7 Mar 2013

The question

To ask the Scottish Government, further to the answer to question S4W-13003 by Fergus Ewing on 5 March 2013, whether it will provide an estimate of the jobs delivered by each of the projects supported by the National Renewables Infrastructure Fund and whether it is on course to create the estimated 28,000 jobs.

The answer

Answered by Fergus Ewing on 27 Mar 2013 · 20 days after it was lodged, 5 days after it was due

In the National Renewables Infrastructure Plan (N-RIP 2) an analysis was carried out to identify the potential direct job benefits arising from the development of all the sites identified. This illustrated that should all the sites be developed for their assumed set of uses Scotland would benefit from 5180 direct manufacturing jobs. This analysis does not include multiplier effects or jobs arising from research and development, installation processes and on-going operation and maintenance jobs. For further detail please refer to N-RIP 2 Report, Section 7.
The projects that have been supported and those under development indicate that this magnitude of direct manufacturing employment is achievable.
The 28,000 jobs is a longer term target. Scotland is already seeing significant progress with announcements from inward investors such as Gamesa, Samsung Heavy Industries, Areva of their intention to locate manufacturing in Scotland and announcements by Scottish companies of investments in the sector.

In the Official Report