Written Question · S4W-13465 · Session 4
Further to the answer to question S4W-12852 by Nicola Sturgeon on 4 March 2013, when it was announced that the two schemes on the A9 would …
The question
To ask the Scottish Government, further to the answer to question S4W-12852 by Nicola Sturgeon on 4 March 2013, when it was announced that the two schemes on the A9 would be brought forward and whether they have been affected by the additional £394 million of capital allocated in the 2012 Autumn Statement.
The answer
The announcement to start construction of the Luncarty to Birnam scheme in 2017 was made on 31 January 2012. The announcement to start construction of the Kincraig to Dalraddy scheme in 2015-16 was made on 26 June 2012.
These two schemes were therefore not affected by the additional £394 million of capital allocated in the 2012 Autumn Statement. The update on the progress of dualling works on the A9 included in the answer to question S4W-12852 was provided as additional information.
These two schemes were therefore not affected by the additional £394 million of capital allocated in the 2012 Autumn Statement. The update on the progress of dualling works on the A9 included in the answer to question S4W-12852 was provided as additional information.