Written Question · S4W-13347 · Session 4
Whether the Aberdeen Western Peripheral Route project cost estimate of £653 million includes (a) all consequential costs for other works re…
The question
To ask the Scottish Government whether the Aberdeen Western Peripheral Route project cost estimate of £653 million includes (a) all consequential costs for other works required to complete the project and (b) money spent in previous years.
The answer
The total scheme cost estimate for the Aberdeen Western Peripheral Route (AWPR) element of AWPR/Balmedie-Tipperty project is £653 million at 2012 prices (excluding VAT) which includes costs associated with design preparation, land purchase, advance works, utility diversions, site supervision, detrunking costs, main works construction costs and risk. The total scheme cost estimate for the AWPR also includes previous expenditure on the project.
In the Official Report
No contribution in the Official Report cites S4W-13347 by reference.