Written Question · S4W-12583 · Session 4
Whether there have been changes to the original timescale for the Aberdeen Western Peripheral Route.
The question
To ask the Scottish Government whether there have been changes to the original timescale for the Aberdeen Western Peripheral Route.
The answer
The protracted legal challenges have resulted in delays to the original timescale and the completion date is now spring 2018. We ensured as much preparatory work as possible was progressed during the legal challenges to ensure that the delay was kept to a minimum.
In the Official Report
No contribution in the Official Report cites S4W-12583 by reference.