Written Question · S4W-12291 · Session 4

What discussions it has had with (a) Highland Council, (b) the emergency services, (c) British Waterways and (d) businesses regarding the u…

Answered Asked by David Stewart Lab Lodged 16 Jan 2013

The question

To ask the Scottish Government what discussions it has had with (a) Highland Council, (b) the emergency services, (c) British Waterways and (d) businesses regarding the use of the Inverness
- Beauly road while the Kessock Bridge is being resurfaced.

The answer

Answered by Keith Brown on 24 Jan 2013 · 8 days after it was lodged, on time

During these essential resurfacing works (due to start on 11 February 2013) delays are inevitable however Transport Scotland has undertaken extensive planning consultation and investment into ensuring traffic disruption is minimised.
Transport Scotland developed a detailed Communications Strategy and as part of this Transport Scotland has had ongoing discussions and liaison with The Highland Council, the emergency services, British Waterways (now Scottish Canals), stakeholders and businesses regarding the use of the Inverness-Beauly road (the A862) during the main phases of work on the Kessock Bridge.
Transport Scotland is not promoting the A862 as a diversion route. The detailed traffic modeling did not predict a significant impact on the A862. It is likely that around 200 to 300 cars will divert via the A862 during a.m. and p.m. peak three hour periods. Discussions with Scottish Canals have taken place to alleviate possible queuing on A862 at Muirton Swing Bridge when the works commence and the canal re-opens following its annual closure for essential maintenance.

In the Official Report