Written Question · S4W-12289 · Session 4
What modelling has been carried out to predict traffic congestion at the approaches to the Kessock Bridge while it is being resurfaced.
The question
To ask the Scottish Government what modelling has been carried out to predict traffic congestion at the approaches to the Kessock Bridge while it is being resurfaced.
The answer
During these essential resurfacing works (due to start on 11 February 2013) delays are inevitable however Transport Scotland has undertaken extensive planning, consultation and investment into ensuring traffic disruption is minimised.
As part of this planning an extensive traffic model covering the road network in and around Inverness has been developed to investigate traffic flows, journey times, delays, congestion, and develop measures to alleviate and minimise delays.
As part of this planning an extensive traffic model covering the road network in and around Inverness has been developed to investigate traffic flows, journey times, delays, congestion, and develop measures to alleviate and minimise delays.