Written Question · S4W-12287 · Session 4
Whether it plans to develop a park and ride facility to alleviate traffic congestion at the Kessock Bridge.
The question
To ask the Scottish Government whether it plans to develop a park and ride facility to alleviate traffic congestion at the Kessock Bridge.
The answer
During these essential resurfacing works (due to start on 11 February 2013) delays are inevitable however Transport Scotland has undertaken extensive planning, consultation and investment into ensuring traffic disruption is minimised.
Measures to alleviate delays include the use of additional permanent car parking at Beauly station (which we are progressing subject to final land agreements) and temporary car parking at Dingwall (use of Ross County Football ground car park) allowing their use for park and ride.
Transport Scotland does not currently have any plans to develop either a temporary or a permanent park and ride facility at Tore. Transport Scotland considered this in detail at an early stage with The Highland Council (using their extensive knowledge of the local network) as part of the permanent mitigation measures on the A82 and A9 which will have significant beneficial effects both during the Kessock Bridge works, and in the long term). There was insufficient evidence to support the long term viability of a park and ride at the Tore site north of the Kessock Bridge.
Measures to alleviate delays include the use of additional permanent car parking at Beauly station (which we are progressing subject to final land agreements) and temporary car parking at Dingwall (use of Ross County Football ground car park) allowing their use for park and ride.
Transport Scotland does not currently have any plans to develop either a temporary or a permanent park and ride facility at Tore. Transport Scotland considered this in detail at an early stage with The Highland Council (using their extensive knowledge of the local network) as part of the permanent mitigation measures on the A82 and A9 which will have significant beneficial effects both during the Kessock Bridge works, and in the long term). There was insufficient evidence to support the long term viability of a park and ride at the Tore site north of the Kessock Bridge.