Further to the answer to question S4W-10835 by Paul Wheelhouse on 12 November 2012, what progress has been made on securing the £200 millio…

Answered Asked by Richard Baker Lab Lodged 11 Dec 2012

The question

To ask the Scottish Government, further to the answer to question S4W-10835 by Paul Wheelhouse on 12 November 2012, what progress has been made on securing the £200 million per annum funding to improve the energy efficiency of Scotland’s homes and tackle fuel poverty.

The answer

Answered by Margaret Burgess on 16 Jan 2013 · 36 days after it was lodged, on time

From 2013-14 the Scottish Government will make available £65 million for the National Retrofit Programme (NRP). In addition we anticipate that contributions from the utility companies will bring the total investment to around £200 million. We are continuing to have discussions with the six obligated suppliers to ensure Scotland gets its fair share of their investment.
Our recent announcement of the successful NRP “go early” pilots demonstrates that positive activity is underway even before the April opening of the scheme. Scottish Government funding of £3.5 million is levering in almost £13 million in energy company funds as part of contracts with Councils and Housing Associations worth £27 million. As well as protecting an estimated 150 jobs over the winter. These pilots will improve the energy efficiency of 2,200 homes.
Officials also continue to have discussions with local authorities and COSLA about the arrangements for next financial year. The pilot schemes demonstrate positive Council engagement and we would encourage authorities to continue to develop their plans for next year and their constructive dialogue with energy companies.

In the Official Report