Further to the answer to question S4W-11127 by Keith Brown on 22 November 2012, how much it spent on (a) the Edinburgh Glasgow Improvement …
The question
To ask the Scottish Government, further to the answer to question S4W-11127 by Keith Brown on 22 November 2012, how much it spent on (a) the Edinburgh Glasgow Improvement Programme, (b) the Borders Railway project, (c) the Paisley Corridor Improvement project, (d) the Waverley Station Redevelopment and (e) its contribution to the Edinburgh Trams project in 2011-12; from which budget lines, and how much was provided from each budget line.
The answer
The budget for Major Public Transport Projects funds specific commitments including the Borders Railway project, the Paisley Corridor Improvement project, the Waverley Station Redevelopment, the Edinburgh Glasgow Improvement Programme and our contribution to the Edinburgh Trams project. It is managed on a programme basis and is therefore not allocated to specific projects.
In the Official Report
No contribution in the Official Report cites S4W-11507 by reference.