Written Question · S4W-11496 · Session 4
Further to the answer to question S4W-03440 by Keith Brown on 27 October 2011, what technical improvements aim to deliver reduced journey t…
The question
To ask the Scottish Government, further to the answer to question S4W-03440 by Keith Brown on 27 October 2011, what technical improvements aim to deliver reduced journey times on lines between Inverness and (a) Aberdeen, (b) Glasgow and (c) Edinburgh.
The answer
The technical improvements required to deliver journey time improvements to the Inverness and Aberdeen and the Highland Central Belt may include additional passing loops, double tracking, signalling enhancements and work on the track and structures to deliver line speed improvements.
In the Official Report
No contribution in the Official Report cites S4W-11496 by reference.