Written Question · S4W-11138 · Session 4

Further to the answer to question S4W-10110 by Margaret Burgess on 31 October 2012, whether the core criteria for bids to the Innovation Fu…

Answered Asked by Elaine Murray Lab Lodged 8 Nov 2012

The question

To ask the Scottish Government, further to the answer to question S4W-10110 by Margaret Burgess on 31 October 2012, whether the core criteria for bids to the Innovation Fund required that, by 31 March 2012, (a) projects should be able to achieve detailed planning consent and (b) housing should be capable of starting on site.

The answer

Answered by Margaret Burgess on 3 Dec 2012 · 25 days after it was lodged, 10 days after it was due

The original core criteria for bids to the innovation fund stated that projects that require planning consent should have detailed planning consent in place, or be able to achieve this by 31 March 2012. In relation to site start it was stated that “housing should be capable of starting on site by 31 March 2012”
It was later recognised that this date may not be achievable for a number of projects and the site start target was extended by two months to May 2012.
Furthermore flexibility has been offered on this revised date where necessary on an individual basis.