Parliament Workbench
Data: Motions & questions to 19 Nov 2026

Written Question · S4W-11136 · Session 4

Further to the answer to question S4W-10110 by Margaret Burgess on 31 October 2012, whether it was a condition of bids to the Innovation an…

Answered Asked by Elaine Murray Lab Lodged 8 Nov 2012

The question

To ask the Scottish Government, further to the answer to question S4W-10110 by Margaret Burgess on 31 October 2012, whether it was a condition of bids to the Innovation and Investment Fund for (a) new council house building and (b) the registered social landlord programme that work must have started on site by the end of March 2012.

The answer

Answered by Margaret Burgess on 3 Dec 2012 · 25 days after it was lodged, 10 days after it was due

It was originally a condition of bids to the fund that the new council house building work must have started on site by the end of March 2012. Similarly for registered social landlord projects it was stated within our published guidelines that work on all approved projects should start on site by the end of March 2012.
It was later recognised that this date may not be achievable for a number of projects and the site start target was extended by two months to May 2012.
Furthermore flexibility has been offered on the revised date where necessary, on an individual basis.

In the Official Report

No contribution in the Official Report cites S4W-11136 by reference.