Written Question · S4W-10780 · Session 4
Further to the answer to question S4W-09791 by Alex Neil on 22 October 2012, whether it will provide a breakdown of the (a) miscellaneous b…
The question
To ask the Scottish Government, further to the answer to question S4W-09791 by Alex Neil on 22 October 2012, whether it will provide a breakdown of the (a) miscellaneous board allocations and (b) provision for contracts and other services below £1 million.
The answer
A breakdown of the Miscellaneous Board Allocations is provided in the following table. This budget line primarily covers support to NHS Boards long-term financial planning developments recognising explicit future commitments within specific Boards e.g. NHS Dumfries and Galloway £4 million for anticipated double running costs for the Dumfries and Galloway Royal Infirmary replacement. Other expenditure within this line includes specific smaller values where final amounts are not yet confirmed e.g. support to the Thalidomide Trust, digital mammography developments.
£
million
NHS Boards Financial Planning Support
20.2
Highlands & Islands Travel Scheme
11.0
Island Boards Partnership
1.9
Direction Bodies – Superannuation Contributions
1.2
PET/CT
1.0
Combat Stress / Support to Veterans
1.0
36.3
The Provision for contracts and other services budget line contains provision for primary care contractors pay awards, contracts for new and extended vaccine programmes and other contracts; the budgets relating to contracts are not disclosed within the budget document as contractual negotiations are not yet completed.
£
million
NHS Boards Financial Planning Support
20.2
Highlands & Islands Travel Scheme
11.0
Island Boards Partnership
1.9
Direction Bodies – Superannuation Contributions
1.2
PET/CT
1.0
Combat Stress / Support to Veterans
1.0
36.3
The Provision for contracts and other services budget line contains provision for primary care contractors pay awards, contracts for new and extended vaccine programmes and other contracts; the budgets relating to contracts are not disclosed within the budget document as contractual negotiations are not yet completed.
In the Official Report