What guidance it issues to proposers of marine environment projects that require environmental impact assessment and multiple consents.

Answered Asked by John Park Lab Lodged 22 Oct 2012

The question

To ask the Scottish Government what guidance it issues to proposers of marine environment projects that require environmental impact assessment and multiple consents.

The answer

Answered by Keith Brown on 31 Oct 2012 · 9 days after it was lodged, on time

We have no formal guidance covering multiple consents.
However, developers are encouraged to approach all relevant consenting bodies at an early stage, including local planning authorities, to discuss their proposals. This can include issues around timing of consents and co-ordination of the scoping opinion in relation to environmental impact assessment where appropriate.

In the Official Report

No contribution in the Official Report cites S4W-10373 by reference.