The question

To ask the Scottish Government, further to the answer to question S4W-04044 by Keith Brown on 28 November 2011, what the reason is for the difference between the figures in the answer and those in David MacBrayne Limited’s financial statements to March 2012.

The answer

Answered by Keith Brown on 31 Oct 2012 · 14 days after it was lodged, on time

The total capital cost to David MacBrayne Ltd, as set out in their financial statements to March 2012, included the cost of works on the two vessels as well as their purchase price.