Further to the answer to question S4O-01319 by Alex Neil on 26 September 2012 (Official Report, c. 11901), which NHS boards have not submit…

Answered Asked by John Pentland Lab Lodged 3 Oct 2012

The question

To ask the Scottish Government, further to the answer to question S4O-01319 by Alex Neil on 26 September 2012 (Official Report, c. 11901), which NHS boards have not submitted and agreed their strategies within three months after the Scottish Medicines Consortium has approved a drug for use.

The answer

Answered by Alex Neil on 25 Oct 2012 · 22 days after it was lodged, on time

Information on NHS board formulary decisions regarding SMC accepted medicines is not held centrally.
The guidance issued under cover of SGHD/CMO(2012)1 published on 13 February 2012 clarified that NHS boards are expected to reach decisions on SMC accepted medicines within 90 days of being advised of the SMC decision; and to publish on their websites formulary decisions within 14 days of the decision being made. NHS boards were asked to confirm that their policies would be updated to reflect this additional guidance by 1 April 2012.
Whilst NHS boards are expected to adhere to the timeframes set out in the guidance, the Scottish Government accepts that there may be situations whereby this is not possible – for example if the medicine requires a protocol to be developed it may not be possible to do so within the set timeframe.
However, where an SMC accepted medicine is not (or not yet) on an NHS board formulary, there is the facility for clinicians to prescribe the medicine via a non-formulary request.

In the Official Report