Written Question · S4W-09743 · Session 4

Further to the answer to question S4W-09445 by Nicola Sturgeon on 19 September 2012, what the anticipated costings are for each project lis…

Answered Asked by Jamie McGrigor Con Lodged 19 Sep 2012

The question

To ask the Scottish Government, further to the answer to question S4W-09445 by Nicola Sturgeon on 19 September 2012, what the anticipated costings are for each project listed.

The answer

Answered by Nicola Sturgeon on 2 Oct 2012 · 13 days after it was lodged, on time

The estimated costs for each of the projects listed in the answer to S4W-09445 are included in the following table.
Project Name
Estimated Cost
(£ Million)
Aberdeen to Inverness Rail Improvements1
250-500
Highland Main Line Improvements1
250-600
Dualling of the A91
1500-3000
A96 Upgrading1
250-500
A82 Improvements1
200-250
HMP Highland1
To be confirmed
Development of Balfour Hospital and Kirkwall Dental Centre (NHS Orkney)1
60-70
Day Services Centre, Raigmore Hospital (NHS Highland)1
25
Scalloway Health Centre (NHS Shetland)2
To be confirmed
St Brendan’s Hospital (NHS Western Isles)
To be confirmed
Notes:
1. The estimated cost figures have been taken from The Infrastructure Investment Plan which can be found at the following link:
http://www.scotland.gov.uk/Publications/2011/12/05141922/0.
2. NHS Shetland has been allocated £2.1 million hub enabling funds to take this project forward. Hub North is currently doing an option appraisal of the potential locations identified for the health centre to inform the process and provide a base for the full business case. The potential options are expected to have significantly different lead implementation times and costs.