Written Question · S4W-09444 · Session 4
What government-funded capital investment projects are underway in the Highlands and Islands and what the completion date is of each projec…
The question
To ask the Scottish Government what government-funded capital investment projects are underway in the Highlands and Islands and what the completion date is of each project.
The answer
An outline of capital investment projects currently underway in the Highlands and Islands region which are funded or part funded by the Scottish Government are included in the following table. In addition there are a range of housing projects currently on site across the Highlands and Islands which are receiving Scottish Government funding.
All projects outlined are being funded by way of traditional capital or by revenue finance through non-profit distributing and hub.
Project Name
Estimated Completion
Inverness College
2015
Western Isles Schools Project
2013
Orkney Islands Schools Investment Programme
2013
Kessock Bridge upgrade
2014
Stornoway-Ullapool Ferry
2014
Wick High School 1
2015
Evie Primary School, Orkney 1
2014
Happy Hansel Primary School, Shetland 1
2014
Milnes Primary School, Moray 1
2014
Campbeltown Grammar School 1
2015
Dunoon/Kirn/St. Mun’s Primary School 1
2014
Daliburgh Primary School, Western Isles 1
Completed 2012
Tain Health Centre
2014
Forres Health Centre
2014
Oban Dental Facility
2013
Mull and Iona Progressive Care Centre
2012
Arnish Plant and Estate Improvements 2
2013
Inverness Campus 2
2013
Forres Enterprise Park – Extension of Roads 2
2013
Forres Enterprise Park – Provide 2 Units 2
2013
Building Development within Forres Enterprise zone 2
2013
Lews Castle development 2
2014
West Highland College infrastructure expansion 2
2013
Kennacraig, Kintyre, Phase 2 – causeway 2
2013
Notes:
1. These schools form part of Phase 1 and 2 of the Scottish Government’s £1.25 billion Scotland’s Schools for the Future School Building Programme.
2. These projects form part of the Scottish Government’s £105 million package of economic stimulus for this year which was announced on 27 June.
All projects outlined are being funded by way of traditional capital or by revenue finance through non-profit distributing and hub.
Project Name
Estimated Completion
Inverness College
2015
Western Isles Schools Project
2013
Orkney Islands Schools Investment Programme
2013
Kessock Bridge upgrade
2014
Stornoway-Ullapool Ferry
2014
Wick High School 1
2015
Evie Primary School, Orkney 1
2014
Happy Hansel Primary School, Shetland 1
2014
Milnes Primary School, Moray 1
2014
Campbeltown Grammar School 1
2015
Dunoon/Kirn/St. Mun’s Primary School 1
2014
Daliburgh Primary School, Western Isles 1
Completed 2012
Tain Health Centre
2014
Forres Health Centre
2014
Oban Dental Facility
2013
Mull and Iona Progressive Care Centre
2012
Arnish Plant and Estate Improvements 2
2013
Inverness Campus 2
2013
Forres Enterprise Park – Extension of Roads 2
2013
Forres Enterprise Park – Provide 2 Units 2
2013
Building Development within Forres Enterprise zone 2
2013
Lews Castle development 2
2014
West Highland College infrastructure expansion 2
2013
Kennacraig, Kintyre, Phase 2 – causeway 2
2013
Notes:
1. These schools form part of Phase 1 and 2 of the Scottish Government’s £1.25 billion Scotland’s Schools for the Future School Building Programme.
2. These projects form part of the Scottish Government’s £105 million package of economic stimulus for this year which was announced on 27 June.