Whether it will provide a breakdown of the capital projects that had altered timescales that resulted in a £30 million capital departmental…
The question
To ask the Scottish Executive whether it will provide a breakdown of the capital projects that had altered timescales that resulted in a £30 million capital departmental expenditure limit (DEL) underspend in 2011-12.
The answer
Capital projects, by nature, are often managed over a number of financial years and as such the Scottish Government recognises that there will, on occasions, be minor and marginal movements to timescales caused by, for example, weather or planning delays, with a subsequent impact on the expenditure profile of the project. This requires a flexible approach to managing capital budgets over time. In respect of financial year 2011-12, the following projects experienced marginal movements in timescales – the Forth Replacement Crossing, the Victoria and Albert Waterfront project, the Port Edgar project, the Stromness Harbour extension project. Accordingly, appropriate budget will be reassigned to these projects in 2012-13 through the Budget Exchange Mechanism.
In the Official Report
No contribution in the Official Report cites S4W-08425 by reference.