Whether the alternative route being proposed in the event of the closure of the A83 at the Rest and Be Thankful will be in place by autumn …

Answered Asked by Jamie McGrigor Con Lodged 27 Jun 2012

The question

To ask the Scottish Executive whether the alternative route being proposed in the event of the closure of the A83 at the Rest and Be Thankful will be in place by autumn 2012.

The answer

Answered by Keith Brown on 19 Jul 2012 · 22 days after it was lodged, on time

The works are programmed to start in August and be completed by November 2012.

In the Official Report

1 contribution mention S4W-08320
  1. 20 Nov 2012
    Topical Question Time
    Jamie McGrigor Con Meeting of the Parliament

    In light of the continual landslides and blockages on the A83 at the Rest and Be Thankful since 2007, with the problem recently exacerbated by heavy rain, when is the relief road due to be completed? On 19 July, in reply to my written ques…