Parliament Workbench
Data: Motions & questions to 26 Nov 2026

Written Question · S4W-07190 · Session 4

What the annual cost was of the 2006 to 2012 Northern Isles ferry services contract.

Answered Asked by Elaine Smith Lab Lodged 11 May 2012

The question

To ask the Scottish Executive what the annual cost was of the 2006 to 2012 Northern Isles ferry services contract.

The answer

Answered by Keith Brown on 24 May 2012 · 13 days after it was lodged, on time

The net annual operating subsidy paid to NorthLink Ferries Ltd is set out in the following table:
Contract Year
(July to June)
Grant
Contract Year 1 (2006-07)
£29.5 million
Contract Year 2 (2007-08)
£28.4 million
Contract Year 3 (2008-09)
£32.3 million
Contract Year 4 (2009-10)
£34.9 million
Contract Year 5 (2010-11)
£37.2 million
Source: NorthLink Ferries Ltd and Transport Scotland.
Information for the current contract year, 2011-12, is not yet available as the contract year ends on 5 July 2012.

In the Official Report

No contribution in the Official Report cites S4W-07190 by reference.