Written Question · S4W-06756 · Session 4
Whether it will publish the needs-based assessment of the Gourock to Dunoon route carried out as part of its review of ferry services.
The question
To ask the Scottish Executive whether it will publish the needs-based assessment of the Gourock to Dunoon route carried out as part of its review of ferry services.
The answer
As noted in the Draft Ferries Plan, we are absolutely committed to providing a ferry service that meets the needs of users on the Gourock to Dunoon town centre to town centre route. Following a fair and open tendering process, the contract awarded in 2011 was the best that could be achieved within very clear European Commission restrictions that only allow for subsidy of a passenger service on this route. Although we appreciate that providing a vehicle service was not a viable option for tenderers, we were disappointed not to be able to continue the vehicle and passenger service. Our clear policy preference is that the service should carry both vehicles and passengers. We will continue to look at more options to achieve that and to improve the overall service and facilities.
Also as noted in the Draft Ferries Plan, where we have sufficiently robust data, we have applied our needs-based assessment to all main communities. For the Gourock to Dunoon route we did not have sufficient information to allow us to apply the methodology in full. We have, however, been able to establish that the town centre to town centre route is consistent with a commuting dependency.
Also as noted in the Draft Ferries Plan, where we have sufficiently robust data, we have applied our needs-based assessment to all main communities. For the Gourock to Dunoon route we did not have sufficient information to allow us to apply the methodology in full. We have, however, been able to establish that the town centre to town centre route is consistent with a commuting dependency.
In the Official Report
No contribution in the Official Report cites S4W-06756 by reference.