Parliament Workbench
Data: Motions & questions to 19 Nov 2026

Written Question · S4W-05394 · Session 4

What the level 4 allocation for adaptations was in the supporting transitions budget line (housing and regeneration) in the Scottish budget…

Answered Asked by Elaine Murray Lab Lodged 1 Feb 2012

The question

To ask the Scottish Executive what the level 4 allocation for adaptations was in the supporting transitions budget line (housing and regeneration) in the Scottish budget 2011-12 prior to the announcement of a further £2 million in the spring revision announced on 31 January 2012.

The answer

Answered by John Swinney on 7 Feb 2012 · 6 days after it was lodged, on time

The level 4 allocation for adaptations within the Housing and Regeneration Supporting Transitions line of the 2011-12 Scottish budget, prior to the announcement of a further £2 million in the Spring Budget Revision, was £8 million.

In the Official Report

No contribution in the Official Report cites S4W-05394 by reference.