What the next stage will be in progressing the Fastlink project.

Answered Asked by Derek Mackay SNP Lodged 14 Nov 2011

The question

To ask the Scottish Executive what the next stage will be in progressing the Fastlink project.

The answer

Answered by Keith Brown on 23 Nov 2011 · 9 days after it was lodged, on time

The next stage of the Fastlink project is to progress the statutory planning processes including Traffic Regulation Orders, a statutory Quality Partnership and planning permission for the infrastructure construction.