The question
To ask the Scottish Executive, further to the answer to question S4W-03748 by Michael Russell on 10 November 2011, what the capital cost of James Watt College's contract was and how much of it (a) has been paid and (b) is due to be paid in each remaining year.
The answer
The capital value of the James Watt College PFI project at contract signature in March 1999 was £8.6 million. The amount paid under the PFI contract to date is £15.6 million. The estimated balance to be paid over the remainder of the PFI contract is £33.6 million.