Parliament Workbench
Data: Motions & questions to 3 Dec 2026

Written Question · S4W-03655 · Session 4

Further to the answer to question S4W-03190 by Keith Brown on 27 October 2011, when it will place the required notice for the Borders Railw…

Answered Asked by Lewis Macdonald Lab Lodged 27 Oct 2011

The question

To ask the Scottish Executive, further to the answer to question S4W-03190 by Keith Brown on 27 October 2011, when it will place the required notice for the Borders Railway project in the Official Journal of the European Commission under the project’s new procurement model.

The answer

Answered by Keith Brown on 7 Nov 2011 · 11 days after it was lodged, on time

The Scottish Government do not intend to publish any further OJEU notice with regard to Borders Railway. As Network Rail will become the Authorised Undertaker for Borders Railway then they will become the procurement authority, and as such, any requirement for a future notice will rest with them.

In the Official Report

No contribution in the Official Report cites S4W-03655 by reference.