Written Question · S4W-03439 · Session 4

Further to the answer to question S3W-38688 by Keith Brown on 11 January 2011, whether it remains its position that the journey time reduct…

Answered Asked by David Stewart Lab Lodged 18 Oct 2011

The question

To ask the Scottish Executive, further to the answer to question S3W-38688 by Keith Brown on 11 January 2011, whether it remains its position that the journey time reductions on the Highland Main Line will be delivered in May 2012 and what the savings will be.

The answer

Answered by Keith Brown on 7 Nov 2011 · 20 days after it was lodged, on time

Journey time reductions on the Highland main line will now take effect from December 2012. This is because the rail industry has agreed not to make any significant changes to the May 2012 GB Rail Timetable to accommodate planning for the Olympic and Paralympic Games.