Parliament Workbench
Data: Motions & questions to 19 Nov 2026

Written Question · S4W-02598 · Session 4

Further to the answer to question S4W-01976 by Stewart Stevenson on 1 August 2011, for what reason it considers that articles 5(1), 6(e), 6…

Answered Asked by Jamie McGrigor Con Lodged 9 Sep 2011

The question

To ask the Scottish Executive, further to the answer to question S4W-01976 by Stewart Stevenson on 1 August 2011, for what reason it considers that articles 5(1), 6(e), 6.8, 8 and 8(c) of the Aarhus Convention do not override the position of the Forestry Commission Scotland regarding the West Loch Awe Timber Haul Route.

The answer

Answered by Stewart Stevenson on 21 Sep 2011 · 12 days after it was lodged, on time

The Aarhus Convention is an international agreement that includes obligations of the signatories in terms of providing access to environmental information and public participation in decision making. The West Loch Awe Timber Haul Route was agreed following an Environmental Impact Assessment (EIA) and associated public consultation.
Environmental information regarding the route has also been supplied under the Environmental Information Regulation.

In the Official Report

No contribution in the Official Report cites S4W-02598 by reference.