Further to the answers to questions S4W-01638 and S4W-01639 by Michael Russell on 10 August 2011, what assessment was made of the criteria …
The question
To ask the Scottish Executive, further to the answers to questions S4W-01638 and S4W-01639 by Michael Russell on 10 August 2011, what assessment was made of the criteria that were used to decide which funding method would apply to schools in the programme, broken down by individual school.
The answer
The government’s overarching objective was to maximise the number of school building projects that could be delivered from the available resources. The decision to fund the majority of the primary and special school projects with capital was driven by accounting rules which require that revenue funded infrastructure projects must remain “off balance sheet”. The level of Scottish Government funding contribution for the primary and special school projects meant that these were not suitable for revenue funding, with the exception of the Dunoon Primary Joint Campus project, which is being procured jointly with Campbeltown Grammar school.
The remaining capital was sufficient to fund seven secondary school projects, which meant the remainder would need to be funded by revenue. These were selected on the basis that a switch to revenue funding either would not result in delays in procurement or may enable a project to commence construction at an earlier date than would otherwise have been possible under a capital programme.
The remaining capital was sufficient to fund seven secondary school projects, which meant the remainder would need to be funded by revenue. These were selected on the basis that a switch to revenue funding either would not result in delays in procurement or may enable a project to commence construction at an earlier date than would otherwise have been possible under a capital programme.
In the Official Report