Parliament Workbench
Data: Motions & questions to 3 Dec 2026

Written Question · S4W-00810 · Session 4

Further to the answer to question S3W-39155 by Keith Brown on 11 February 2011, when work will commence on the (a) Hardgrove to Kinmount an…

Answered Asked by Jim Hume LD Lodged 14 Jun 2011

The question

To ask the Scottish Executive, further to the answer to question S3W-39155 by Keith Brown on 11 February 2011, when work will commence on the (a) Hardgrove to Kinmount and (b) Dunragit Bypass A75 improvements.

The answer

Answered by Keith Brown on 27 Jun 2011 · 13 days after it was lodged, on time

The statutory process for the Hardgrove to Kinmount and Dunragit Bypass projects have been completed and both will be taken forward for construction at the earliest possible opportunity.

In the Official Report

No contribution in the Official Report cites S4W-00810 by reference.