Whether it remains committed to Reston and East Linton railway stations being operational by December 2016.

Answered Asked by Jim Hume LD Lodged 18 Nov 2015

The question

To ask the Scottish Government whether it remains committed to Reston and East Linton railway stations being operational by December 2016.

The answer

Answered by Derek Mackay on 25 Nov 2015

The Scottish Government is committed to providing services that can call at Reston and East Linton subject to the completion of the stations by the promoters and the granting of necessary track access rights, however, the date of December 2016 was not given as a confirmed date for the stations and the services commencing. Rather this was the earliest possible date based on the programme information available at that time.