The question

To ask the Scottish Government how it will ensure that local authorities will be given the full revenue and capital costs necessary to implement its early years and childcare initiative.

The answer

Answered by Aileen Campbell on 25 Jun 2014

The Scottish Government is committed to fully funding the agreed costs of our early learning and childcare policy. We have already committed significant revenue and capital funding to local authorities. Full details can be found in the Financial Memorandum and Supplementary Financial Memorandum for the Children and Young People (Scotland) Act 2014. Local authorities have been notified of the allocation and distribution of this funding.
We have proposed a further capital allocation of £61 million to local authorities for the additional two year olds who will become eligible from August 2014 and August 2015, and we continue to work with COSLA to agree a final sum.