What assessment Transport Scotland has made of medium and long-term traffic volumes at the M8/M9 interchange at Newbridge.

Answered Asked by Colin Keir SNP Lodged 28 Aug 2013

The question

To ask the Scottish Government what assessment Transport Scotland has made of medium and long-term traffic volumes at the M8/M9 interchange at Newbridge.

The answer

Answered by Keith Brown on 5 Sep 2013

The Strategic Transport Project Review assessed the future performance of the transport network across Scotland.
In the Newbridge area we are delivering the Queensferry Crossing (including a bus lane on the M9) and the Edinburgh to Glasgow Rail Improvement Programme and work is also underway to identify the optimum deployment of managed motorway technologies on the most congested parts of the Scottish Trunk Road network, including the M8 and A720.
We are also working with local authorities to deliver further public transport improvements at the Newbridge roundabout.

In the Official Report