Further to the answer to question S3W-39113 by Alex Neil on 7 February 2011, what the estimated cost is of guaranteeing the loan finance of…

Answered Asked by Mary Mulligan Lab Lodged 25 Feb 2011

The question

To ask the Scottish Executive, further to the answer to question S3W-39113 by Alex Neil on 7 February 2011, what the estimated cost is of guaranteeing the loan finance of local authorities involved in the first tranche of National Housing Trust houses.

The answer

Answered by Alex Neil on 11 Mar 2011 · 14 days after it was lodged, on time

Based on modelling by the Scottish Futures Trust, with input from the Scottish Government, it is currently estimated that the cost of guaranteeing the loan finance of local authorities involved in the first tranche of the National Housing Trust initiative (NHT) will be approximately £2,500 per unit. The actual level of funding set aside to support the scheme will depend on the number and details of the homes supported through the first phase of procurement, and the financial assessments of developments at the point they are finally approved to proceed.