On what date building work commenced on phase 2 of the Gartcosh crime campus.
The question
To ask the Scottish Executive on what date building work commenced on phase 2 of the Gartcosh crime campus.
The answer
The stage 2 contractor commenced work on the construction of the Scottish Crime Campus on 21 February 2011.