Written Question · S3W-38636 · Session 3
Further to the answer to question S3W-37929 by John Swinney on 16 December 2010, what the status of the 2011 National Planning Framework Mo…
The question
To ask the Scottish Executive, further to the answer to question S3W-37929 by John Swinney on 16 December 2010, what the status of the 2011 National Planning Framework Monitoring Report will be in project decision-making and development plan preparation.
The answer
The purpose of the 2011 National Planning Framework Monitoring Report is to keep the National Planning Framework under review, so the weight attached to it in decision-making and development plans will be for the decision maker. The second National Planning Framework remains the Scottish Government''s spatial plan for Scotland and policy until it is replaced.
In the Official Report
No contribution in the Official Report cites S3W-38636 by reference.