(a) how often and (b) for how long the Cabinet Sub-Committee on Scottish Government Resilience dealing with the 2010-11 winter conditions h…
The question
To ask the Scottish Executive (a) how often and (b) for how long the Cabinet Sub-Committee on Scottish Government Resilience dealing with the 2010-11 winter conditions has met between 11 November and 8 December 2010.
The answer
Between 11 November and 8 December 2010, the Cabinet Sub-Committee on Scottish Government Resilience met on the following occasions and discussed the 2010-11 winter conditions. Each meeting lasted between one and two hours:
Date
| Time
24 November 2010
| 10.45 am
25 November 2010
| 10.00 am
26 November 2010
| 2.30 pm
27 November 2010
| 11.00 am
29 November 2010
| 11.00 am
30 November 2010
| 1.00 pm
1 December 2010
| 12.30 pm
2 December 2010
| 1.00 pm
3 December 2010
| 3.00 pm
4 December 2010
| 11.00 am
5 December 2010
| 11.00 am
6 December 2010
| 3.00 pm
6 December 2010
| 8.30 pm
7 December 2010
| 10.00 am
7 December 2010
| 3.30 pm
8 December 2010
| 11.00 am
Since 8 December, meetings of the Cabinet Sub-Committee have continued on a daily basis.
In addition to meetings of the Cabinet Sub-Committee on Scottish Government Resilience, 15 other ministerial resilience meetings with external organisations took place during the period concerned to discuss the 2010-11 winter conditions.
Date
| Time
24 November 2010
| 10.45 am
25 November 2010
| 10.00 am
26 November 2010
| 2.30 pm
27 November 2010
| 11.00 am
29 November 2010
| 11.00 am
30 November 2010
| 1.00 pm
1 December 2010
| 12.30 pm
2 December 2010
| 1.00 pm
3 December 2010
| 3.00 pm
4 December 2010
| 11.00 am
5 December 2010
| 11.00 am
6 December 2010
| 3.00 pm
6 December 2010
| 8.30 pm
7 December 2010
| 10.00 am
7 December 2010
| 3.30 pm
8 December 2010
| 11.00 am
Since 8 December, meetings of the Cabinet Sub-Committee have continued on a daily basis.
In addition to meetings of the Cabinet Sub-Committee on Scottish Government Resilience, 15 other ministerial resilience meetings with external organisations took place during the period concerned to discuss the 2010-11 winter conditions.
In the Official Report
No contribution in the Official Report cites S3W-38184 by reference.