Parliament Workbench
Data: Motions & questions to 19 Nov 2026

Written Question · S3W-38080 · Session 3

What the legal set-back distances are for the construction of wind turbines from (a) individual properties and (b) settlements.

Answered Asked by Karen Whitefield Lab Lodged 6 Dec 2010

The question

To ask the Scottish Executive what the legal set-back distances are for the construction of wind turbines from (a) individual properties and (b) settlements.

The answer

Answered by Keith Brown on 15 Dec 2010 · 9 days after it was lodged, on time

There are no legal set-back distances. Scottish Planning Policy recommends a 2km separation distance between areas of search for wind farms and the edge of cities, towns and villages. The Scottish Parliament''s Public Petitions Committee has supported this position as a guide rather than a rule in closing petition PE1328; the petition summary can be accessed on the Scottish Parliament''s website: http://www.scottish.parliament.uk/business/petitions/docs/PE1328.htm.

In the Official Report

No contribution in the Official Report cites S3W-38080 by reference.