Written Question · S3W-37565 · Session 3

Further to the answer to question S3W-37092 by Stewart Stevenson on 3 November 2010, whether it will provide a breakdown of the rail infras…

Answered Asked by Jamie Hepburn SNP Lodged 16 Nov 2010

The question

To ask the Scottish Executive, further to the answer to question S3W-37092 by Stewart Stevenson on 3 November 2010, whether it will provide a breakdown of the rail infrastructure and other transport programmes investment by (a) type of investment and (b) project.

The answer

Answered by Stewart Stevenson on 25 Nov 2010 · 9 days after it was lodged, on time

The breakdown of the rail infrastructure and other transport programmes investment budgets by (a) type of investment and (b) project is shown below.
(a) The rail infrastructure represents the network grant which the Office of Rail Regulation judged was necessary to fund Network Rail for renewals, enhancements, maintenance and operating expenditure in Scotland. Network Rail''s income is principally recovered through track access charges paid by passenger and freight operators, station access charges, and network grants paid by the Department for Transport and the Scottish Government to Network Rail in lieu of access charges.
Description
| 2006-07
| 2007-08
| 2008-09
| 2009-10


| £ million
| £ million
| £ million
| £ million

Rail Infrastructure
| 357.90
| 366.50
| 382.70
| 364.30

(b) The budget for major public transport projects is not allocated across individual projects. It funded specific commitments including the Waverley Station redevelopment, the Stirling“Alloa“Kincardine link and our contribution to the Edinburgh trams project.
Description
| 2006-07
| 2007-08
| 2008-09
| 2009-10


| £ million
| £ million
| £ million
| £ million

Other Transport Programmes
| 158.00
| 264.70
| 157.70
| 171.86

In the Official Report

No contribution in the Official Report cites S3W-37565 by reference.