Written Question · S3W-37465 · Session 3
With what flood prevention schemes it is assisting the City of Edinburgh Council, broken down by (a) financial costs and (b) location.
The question
To ask the Scottish Executive with what flood prevention schemes it is assisting the City of Edinburgh Council, broken down by (a) financial costs and (b) location.
The answer
Funding for flood risk management is no longer ring-fenced to specific schemes but is included within the overall level of capital support provided to local government. This provides local authorities with the flexibility to allocate the financial resources available to them on the basis of local needs and priorities having first fulfilled their statutory obligations and jointly agreed set of national and local priorities.
In 2007, the City of Edinburgh Council had two confirmed flood prevention schemes, the Braid Burn and the Water of Leith. The Braid Burn scheme had been awarded a grant at 80% of the estimated cost of £28,506,520.09 in quarterly instalments to the end of 2011-12. The relevant amounts are translated into the general capital grant as part of the capital support over the period 2008-2011.
The Water of Leith Scheme had been awarded a grant towards costs of £5.5m up to March 2008. So the general capital grant took account of the remaining estimated costs, £40.35m, spread over 6 years. In addition, in 2010-11 the level of capital support took into account the level of flood risk in the Council''s area.
It is however for the City of Edinburgh Council to allocate resources for flood risk management from the overall resources available to it.
In 2007, the City of Edinburgh Council had two confirmed flood prevention schemes, the Braid Burn and the Water of Leith. The Braid Burn scheme had been awarded a grant at 80% of the estimated cost of £28,506,520.09 in quarterly instalments to the end of 2011-12. The relevant amounts are translated into the general capital grant as part of the capital support over the period 2008-2011.
The Water of Leith Scheme had been awarded a grant towards costs of £5.5m up to March 2008. So the general capital grant took account of the remaining estimated costs, £40.35m, spread over 6 years. In addition, in 2010-11 the level of capital support took into account the level of flood risk in the Council''s area.
It is however for the City of Edinburgh Council to allocate resources for flood risk management from the overall resources available to it.