Written Question · S3W-37400 · Session 3
Further to the answer to question S3W-37107 by Stewart Stevenson on 3 November 2010, whether work on the transport plan for the 2014 Ryder …
The question
To ask the Scottish Executive, further to the answer to question S3W-37107 by Stewart Stevenson on 3 November 2010, whether work on the transport plan for the 2014 Ryder Cup will include consideration of the reopening of Blackford railway station.
The answer
Transport Scotland have already considered a proposal to reopen Blackford railway station earlier this year as part of their assessment of AECOM''s independent review published in April 2010 on behalf of the Campaign to Open Blackford Railway Station Again.
The assessment concluded that the proposal did not fully integrate with the current and committed operation of the rail network. Due to the close proximity of Gleneagles station, Transport Scotland''s investment hierarchy points to making best use of existing stations and the Ryder Cup transport planning will consider proposed improvements to Gleneagles station rather than reopening Blackford station.
The assessment concluded that the proposal did not fully integrate with the current and committed operation of the rail network. Due to the close proximity of Gleneagles station, Transport Scotland''s investment hierarchy points to making best use of existing stations and the Ryder Cup transport planning will consider proposed improvements to Gleneagles station rather than reopening Blackford station.
In the Official Report
No contribution in the Official Report cites S3W-37400 by reference.