The question

To ask the Scottish Executive how it plans to develop the Stranraer-Glasgow rail route.

The answer

Answered by Stewart Stevenson on 3 Nov 2010 · 8 days after it was lodged, on time

Stena Line is due to re-locate from Stranraer to new facilities at Cairnryan in late autumn 2011. This has provided opportunities to improve rail provision to better match local needs. As a result Transport Scotland has asked Scotrail to work on improving the timetable for south west Scotland, including services to and from Stranraer, to deliver improved service frequency and new journey opportunities
The proposed timetable is anticipated to take effect in December 2011.